When are Cost Centers filled in automatically on a Purchase Invoice created from a Construction contract, and why are they sometimes left empty?
Cost centers are filled in only on an invoice created directly from the purchase options, with assignment enabled for Purchase Invoices and a cost center defined at the selected level.
- Some lines can be filled in while others stay empty on the same invoice, if some items have a cost center and others do not.
- Enabling the configuration after you open the form is not enough; create the invoice again from the contract.
| Reason | Solution |
|---|---|
| Purchase Invoices is not enabled in Cost Center Assignment. | Enable it from Accounting Settings. |
| The invoice is converted from a Purchase Order or created manually. | Select the cost center manually or create the invoice from the contract. |
| The level is Project and the project has no cost center. | Add a cost center to the project. |
| The level is Work Item or Items and the item has no cost center. | Select the cost center manually for the line. |
Are cost centers filled in on a Purchase Order and a Purchase Quotation created from the contract?
Assignment to more than one cost center is available only in a Purchase Invoice. In a Purchase Order and a Preview Purchase Quotation, the single Cost Center field is filled in if the line has only one cost center; if the item is distributed across more than one cost center, it stays empty. When you convert the Purchase Order to an invoice, the cost centers are not filled in automatically.
- Purchase Requests and requests for quotations do not carry cost centers at all.
- The reason is that the Purchase Order and Preview Purchase Quotation forms contain a single Cost Center field for each line, and they do not support percentage-based assignment.
- If you need precise assignment, create the Purchase Invoice directly from the contract instead of converting it from the Purchase Order.
What is the default Cost Tracking Level, and what is the difference between “Project,” “Items,” and “Work Item”?
The Cost Tracking Level field in a Construction Project is optional and has no default value; if you leave it empty, it is treated as Project. You change it in the project details in Construction Projects.
- Changing the level affects only the invoices created after the change.
- The field appears in the Construction Project form within its details, and you can edit it at any time.
- Cost centers for the project or for the items are created and managed from Cost Centers.
| Level | Cost center for Purchase Invoice lines |
|---|---|
| Project | The project’s cost center for all lines |
| Items | The cost center of the sub-item that is the direct parent of the Work Item |
| Work Item | The Work Item’s cost center |