Why doesn’t the Settle Retention option appear in the Add menu of a Construction Project?
Settle Retention appears in the Add menu on a Construction Project file only when all three conditions are met: you have the Add Incomes permission, the project is a Construction Project, and the project has a Contract that was activated and has a Retention Percentage greater than zero.
- Open the Contract from Contracts and make sure its status is Active, or that it was activated previously and then closed or canceled.
- Check the Retention in the Contract details; you cannot change it after activation because it is part of the locked Financial Details.
- The Add Incomes permission is added from Roles; the action does not need the permission to view Invoices to appear, but that permission is required to see the Invoices in the panel.
| Reason | Solution |
|---|---|
| You do not have the Add Incomes permission. | Add it to your role from Roles. |
| The project’s Contract has not been activated (Draft or issued). | Activate the Contract from its page in Contracts. |
| The Contract has no Retention. | There are no amounts to settle. |
| The project has no Contract. | Create a Contract for the project and activate it. |
🛈
Note: The action remains visible after the Contract is closed or canceled, because the condition is that the Contract was activated at some point before.