What data transfers from a Cost Sheet to the Construction Quotation created from it?
When you click Create Estimate, the Estimate form opens pre-filled with the following: the same Cost Sheet, the Duration, the start and end dates, the Project or Bid, the Client, the Taxes, and the quantities table. Materials/labor are not carried over because the Estimate quantities table does not include them. You can edit the editable fields before you Save, and the Client stays disabled because it is taken from the sheet.
- The Estimate is saved with the status Issued when you click Save, and it appears in the Estimates tab in the sheet.
- Its creation is recorded in the sheet’s Activity Log.
- If you change the Currency in the Estimate, the prices are converted according to the defined exchange rates.
- You can create multiple Estimates from the same sheet, and all of them appear in the Estimates tab.
- The sheet’s dates take precedence over the Project dates in the Estimate.