How Are the Contract Progress Percentages (Certified to Date, Previous, Current) Calculated on the Payment Certificate Page?

All three percentages are measured against the total contract quantity, net of reverse certificates. Previous is what earlier certificates certified (approved or invoiced ones only), net of reverse certificates in Credited status on them; Current is this certificate's own quantity in any status except Rejected; Certified to Date is Previous plus Current minus what was reversed from this certificate, and Current is added only once the certificate is approved or invoiced; until then it equals Previous.

  • Example: a contract of 1,000 units, earlier certificates certified 300 units of which 50 were reversed, and this certificate certifies 200: Previous 25%, Current 20%, Certified to Date 45% once the certificate is approved, and 25% while it is draft or issued.
  • Only work items still on the contract BoQ are counted; if the contract's work items were changed after the certificate so its lines are no longer on the contract BoQ, their quantities are not counted and the percentages can show 0%.
  • The remaining quantity shows per item in the Remaining column of the certificate items table, not in the progress bar.
  • The field is in the Details tab of the certificate page under Payment Certificates.
🛈

Note: The progress bar in the contract header is calculated the same way from certified quantities (approved or invoiced certificates net of Credited reverse certificates) against the total contract quantity, but it covers all the contract's certificates to date, while the certificate field shows where the contract stood at this certificate.