When Do Add Advance Payment, Add Payment Certificate, Close and Settle Retention Appear on the Construction Contract Page, and Why Are They Sometimes Hidden?
The primary buttons in the construction contract header follow the contract's stage, and each needs a specific permission. A missing button means the contract is not at that stage, the condition is not met, or you lack the permission.
| Button | Shown when | Permission |
|---|---|---|
| Issue | The contract is Draft. | Edit & Delete All Construction Contracts or Edit & Delete His Own (Created) Construction Contracts |
| Activate | The contract is Issued; activation works only when the contract is linked to a project. | Approve & Reject Construction Contracts |
| Advance Payments (a menu with Add Advance Payment and Assign Advance Payment) | After creation, when the contract has an advance payment value and no advance payment invoice was added. | Add Invoices with View All Clients, or adding invoices for your own clients only when the contract's client is one of yours |
| Add Payment Certificate | After activation and before progress reaches 100%. | Add Payment Certificates |
| Close | At 100% progress or more, replacing Add Payment Certificate. | Edit & Delete All Construction Contracts or Edit & Delete His Own (Created) Construction Contracts |
| Settle Retention | With Close at 100% or more, only when the contract is linked to a project, its Retention rate is above zero, and the project's invoices carry unsettled retention. | Add Income |
🛈
Note: Permissions are granted from Employee Roles. After the advance payment invoice is added the Advance Payments menu disappears from the primary buttons, and once all retention is settled Settle Retention disappears. Closing the contract sets the linked project to Completed.