How are material quantities calculated when importing a work item from a cost sheet into a work item template?
Each material or service quantity is taken from the cost sheet's Cons./Unit, not its total quantity, because a template's work item quantity is always 1. Unit, unit cost and item are copied with it.
- Example: plastering of 200 m² consuming 5 kg cement per m² (1,000 kg total) is imported with a cement quantity of 5.
- When the template is later used in a cost sheet, these quantities are multiplied by the work item quantity there.
- The source cost sheet does not change.