Is the whole BoQ import cancelled if one row fails, or are the valid rows applied?
One failed row does not cancel the import: in cost sheets, bids, construction quotations and contracts, Review errors lists the rejected rows and why, then you choose:
- Skip & Continue: only the valid rows are imported.
- Upload Another File: after fixing the file.
- Rows under a rejected row are skipped too, with «Skipped because parent row … has errors.»
- The BoQ changes only after the import, and items are kept only after the record is saved.
| The whole file is rejected when | Message |
|---|---|
| The file is over 50 MB or not XLSX/CSV | «File size exceeds the maximum allowed limit of 50 MB.» |
| The file has no rows | «The file does not contain any BoQ rows.» |
| The first row is not a main tender | «The file must start with a Main Tender row (e.g. Number 1). Row … is "…".» |
| A mapped column is missing or repeated | «Column "…" was not found in the file.» |