The “Purchase Options” Button in the Work Items Tab of the Construction Contract
The Purchase Options button in the fixed bar at the bottom of the Work Items tab in the construction contract creates a ready purchase document from the materials you select, without re-entering the materials, their quantities, and units. Use it when you want to buy the contract materials from suppliers, whether you start the cycle with a purchase request or jump directly to a purchase order or a purchase invoice. This guide explains the conditions for the button to appear, the available documents and the permission of each, what is transferred from the contract, and the messages and restrictions.
Contents
Before You Start
- Enable the Construction app, the Purchase Cycle app for the purchase request, quotation request, purchase quotation, and purchase order, and the Inventory app for the purchase invoice.
- The contract status must be Active, and it must be linked to a Cost Sheet.
- The cost sheet must contain materials (products of the product type, not a service).
- The supplier must be added in advance if you will create a purchase quotation, a purchase order, or a purchase invoice.
- To fill the cost centers automatically in the purchase invoice, enable Purchase Invoices under Item-Level Cost Center Assignment by Transaction Type in General Accounting Settings.
Opening Purchase Options
- From the main menu, click Construction, then Contracts, and open the contract.
- Click the Work Items tab (it appears after the contract is activated).
- Select the work items or the materials from the checkboxes; click the arrow next to the work item to view its materials.
- A fixed bar appears at the bottom of the screen with the number of selected items and the Export to Excel, Purchase Options, Expand Group, and Collapse Group buttons.
- Click Purchase Options and choose the document. The add form of the document opens with the materials.
When the Button Appears
| Condition | If Not Met |
|---|---|
| At least one item is selected | The bar doesn’t appear at all. |
| The contract is linked to a cost sheet | The button is hidden. |
| The contract status is Active | The button is hidden (a Draft, Cancelled, or Closed contract). |
| The permission and app of at least one document | The button is hidden. The list shows only the documents you are allowed to create. |
Available Documents and the Permission of Each
| Document | Permission | App | Opens | After Saving / Cancelling |
|---|---|---|---|---|
| Purchase Request | Manage Purchase Requests | Purchase Cycle | The add purchase request form | Saving works as usual; cancelling takes you back to Purchase Requests |
| Quotation Request | Manage Purchase Quotations | Purchase Cycle | The quotation request form (more than one supplier) | Cancelling takes you back to Quotation Requests |
| Purchase Quotation | Manage Purchase Quotations | Purchase Cycle | The add purchase quotation form | Cancelling takes you back to Purchase Quotations |
| Purchase Order | Manage Purchase Orders | Purchase Cycle | The add purchase order form linked to the project | Cancelling takes you back to Purchase Orders |
| Purchase Invoice | Add New Purchase Invoice | Inventory | The purchase invoice form with filled cost centers | Saving opens the invoice; cancelling takes you back to Purchase Invoices |
🛈
Note: The Manage Purchase Quotations permission alone allows both Quotation Request and Purchase Quotation. Permissions are granted from Roles.
What Is Transferred from the Contract to the Document
- Only materials are transferred from the cost sheet linked to the contract. Any product of the service type is excluded without a message.
- Selecting a work item transfers all its materials in the cost sheet, and the item itself isn’t added as a line in the document. Selecting the item and some of its materials together doesn’t repeat the material.
- For each line: the product, the Quantity (the planned quantity in the cost sheet, rounded to the number of decimal places allowed in your account), the unit, and the conversion factor.
- The same material with the same unit in more than one work item is combined in one line with the total quantities; with different units, it’s split into a line for each unit.
- The document is linked to the contract’s project automatically.
- The quantities are suggestions only, and you can edit them or delete any line. The system doesn’t deduct what was purchased before; each time, the full planned quantity is suggested.
What Happens Automatically
- The system saves the selected materials temporarily for 15 minutes for you only, then opens the form. Refreshing the page during this time doesn’t lose your selection.
- The contract status, its work items, and the cost sheet don’t change when creating any purchase document.
- Every document converted later from the created document (such as quotation request → purchase quotation → purchase order → purchase invoice) stays linked to the contract’s project.
- In the purchase invoice, the cost centers for each line are filled according to the Cost Tracking Level in the project.
Restrictions
- Services aren’t transferred to any purchase document.
- You can’t start from a contract that isn’t active or isn’t linked to a cost sheet.
- You can’t select items from another contract, or sub-tenders (main items) only; items that don’t belong to the contract are rejected.
- You must have permission to view the contract; a user with permission to view only their own contracts can’t start from a contract created by someone else.
- Distributing the cost centers over more than one center is available in the purchase invoice only.
- In the purchase request and the quotation request, the same product isn’t accepted in two lines; if a material is split because of different units, delete one of the two lines or unify the unit before saving.
Why Can’t I…?
| Problem | Cause | Solution |
|---|---|---|
| The button doesn’t appear | The contract isn’t active, has no cost sheet, or you don’t have any purchase permission | Review the conditions above |
| A specific document doesn’t appear in the list | You don’t have its permission, or its app isn’t enabled | Request the permission or enable the app |
| Some materials are missing from the form | The materials are services or weren’t selected | Select the required materials |
| The quantity is greater than what actually remains | The suggested quantity is always the planned one | Edit the quantity manually |
Error Messages and Their Solutions
| Message | Cause | Solution |
|---|---|---|
| Purchase transactions cannot be created for services. | Everything you selected is services, or work items that contain only services. | Select at least one material. |
| The selected work items are no longer available. Please go back to the contract and select them again. | More than 15 minutes have passed since clicking Purchase Options, or the link was opened by another user. | Go back to the contract, select the materials, and click Purchase Options again. |
| Purchase transactions require an active contract. | The contract status is no longer Active. | Open an active contract. |
| Contract is not linked to a cost sheet. | The contract isn’t linked to a Cost Sheet. | Use a contract linked to a cost sheet. |
| Select at least one work item or material. | No item was selected. | Select a work item or a material. |
| Items … do not belong to this contract. | One of the selected items doesn’t belong to this contract (such as a sub-tender or an item from another document). | Select the work items and materials from the same contract’s tab only. |
| You are not allowed to access this page | You don’t have the permission to view the contract or the document’s permission. | Request the permission from Roles. |
Frequently Asked Questions
Can I start with a purchase invoice directly?
Yes; choose Purchase Invoice from the list.
Can I create more than one document from the same contract?
Yes, without a limit; and the system doesn’t deduct the previously purchased quantities.
Are services transferred?
No; only materials.
Does the contract change after creating a purchase document?
No; the contract’s status and items don’t change.
Are the documents linked to the project?
Yes; the document and everything converted from it.
How long does the selection stay saved?
15 days.