Why doesn’t the Settle Retention option appear in the Add menu of a Construction Project?

Settle Retention appears in the Add menu on a Construction Project file only when all three conditions are met: you have the Add Incomes permission, the project is a Construction Project, and the project has a Contract that was activated and has a Retention Percentage greater than zero.

  • Open the Contract from Contracts and make sure its status is Active, or that it was activated previously and then closed or canceled.
  • Check the Retention in the Contract details; you cannot change it after activation because it is part of the locked Financial Details.
  • The Add Incomes permission is added from Roles; the action does not need the permission to view Invoices to appear, but that permission is required to see the Invoices in the panel.
Reason Solution
You do not have the Add Incomes permission. Add it to your role from Roles.
The project’s Contract has not been activated (Draft or issued). Activate the Contract from its page in Contracts.
The Contract has no Retention. There are no amounts to settle.
The project has no Contract. Create a Contract for the project and activate it.

🛈

Note: The action remains visible after the Contract is closed or canceled, because the condition is that the Contract was activated at some point before.